Request For Qualification/Proposal (RFQ/P)

New Maintenance & Operations Building

Lodi Unified School District (“District”) is seeking to prequalify design-build entities (“DBE”) or design-build teams to submit proposals to design and construct the District’s New Maintenance and Operations Building (“Project”).

Instructions for submitting rfq/p

RFQ/P SCHEDULE OF EVENTS SUMMARY:

The District may change the dates on this schedule without prior notice.

Date

Event

Time

9/6/2018

Advertise and Release of RFQ

 

9/18/2018

Non-Mandatory Pre-Submittal Conference

2:00 pm

9/21/ 2018

Last Day to Receive Written Questions from Respondents

2:00 pm

9/27/2018

Last Day for District to Issue Addenda

 

10/4/2018

Deadline to Submit SOQ

2:00 pm

10/11/2018

Notice to Pre-Qualified Respondents and Issue RFP to Shortlist

 

10/15/2018

Confidential Meetings with Three Proposers (week of)

 

10/23/2018

Deadline to Submit RFP Questions

 

10/25/2018

Publish Answers to Questions via Addendum

 

11/6/2018

Final Proposals Due

 

11/12/2018

Anticipated Interviews if Applicable (week of)

 

11/20/2018

Board of Education Approval

 

11/30/2018

Anticipated Date of Contract Execution and issue NTP

 

7/1/2019

Anticipated Date of Submission of Final Design to City of Lodi and all Local Jurisdictional Agencies

 

 

THANK YOU FOR YOUR INTEREST IN THIS EXCITING PROGRAM!

Bear Creek High School Jive Wiring Infrastructure Project

Lodi Unified School District, herein referred to as “Client” or “District” is requesting proposals from qualified Jive Wiring Infrastructure installing contractors, herein referred to as “Contractor” to provide Jive Wiring Infrastructure installation services for a District-wide VOIP project.

Information for submitting RFP

RFP SCHEDULE OF EVENTS SUMMARY:

Event / Occurrence

Deadline

Time

District Issues RFP

September 12, 2018

 

Site Visit (see section 2.2 for schedule)

September 18, 2018

9:00 AM

Deadline for Contractor to submit questions regarding this RFP

September 21,2018

4:30 PM

Deadline for Contractors to submit Proposal

October 4, 2018

4:30 PM

District to interview Contractor(s) – (Optional)

October 11, 2018

 

District to finalize recommendation for District Board of Education

November 12, 2018

 

District Board of Education approves successful Contractor

November 20, 2018

 